Road Paving

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Weed Ave 

As we approach the 2023 paving season, the City is eagerly awaiting the completion of the recently commissioned city-wide road conditions report. The report was commissioned to establish a multi-year priority list for road paving that will be based off the existing road conditions, without traffic considerations. This approach is to ensure residential neighborhoods are not disproportionately disadvantaged in determining paving priorities. The final report will be completed shortly, but in the meantime please see the following updates:

  • Budget: The Mayor has maintained the 2022 level of funding to support the Pave Stamford initiative, which aims to pave over 200 roads in four years. The 2022 paving season was a success, doubling the previous year’s total of roads paved with over 70 roads completed by mid-November 2022. Barring any decreases by city boards to this account during this year’s budget process, we anticipate staying on track to achieve our goal of completing over 200 roads in four years. 
  • Utility Coordination: The Operations Department is formalizing an internal Standard Operating Procedure which will leverage utility paving contributions to pursue curb-to-curb paving on all projects.  We will also target a paving completion timeline of no less than 90 days following the completion of a utility coordination paving project.
  • Paving List:  The City has identified the first 36 roads which will commence April 2023. The list was compiled based on remaining roads from previous assessments and utility coordination projects. We anticipate adding additional roads for the 2023 season following the completion of the city-wide road conditions report.

 


 

2023 City of Stamford Initial Paving List

 

Count

Road/street Name

Description

Utility Contribution

1

Avery Street

Cove-to-Charles

YES

2

Bennington Ct

Entire Road

NO

3

Cove Road

Willowbrook-to-Shippan

NO

4

Dale Street

Entire Road

YES

5

Dora Street

Cove-to-Middlebury St.

NO

6

Downs Ave

Shippan-to-Dead end

YES

7

Echo Hill Dr.

Entire Road

NO

8

Fieldstone Circle

Entire Road

NO

9

Fieldstone Lane

Entire Road

NO

10

Fieldstone Road

Entire Road

NO

11

Fieldstone Terrace

Entire Road

NO

12

Friar Truck Lane

Entire Road

NO

13

Grey Birch Road

Long Ridge-to-top of hill

NO

14

Houston Terrace

Matthews-to-E. Main

YES

15

Larkin Street

Entire Road

NO

16

Lee Street

Entire Road

NO

17

Little John Lane

Entire Road

NO

18

Lockwood Ave

Intersections

YES

19

Myrtle Ave @ William

Section @ William Street

YES

20

Nottingham Drive

Entire Road

NO

21

Poplar Street

Entire Road

NO

22

Progress Drive

Entire Road

NO

23

Ralph Street

Downs-to-Dead end

YES

24

Ralsey Road

Shippan-to-Ralsey Rd. S.

YES

25

Research Drive

Entire Road

NO

26

Robin Hood Road

Entire Road

NO

27

St. Benedict Circle

Entire Road

YES

28

Stamford Ave

Ralsey-to-Sagamore

YES

29

Viaduct Road

Entire Road

NO

30

W. Haviland Lane

Entire Road

NO

31

Warren Street

Entire Road

YES

32

West View Lane

Entire Road

NO

33

Whittaker Street

Downs-to-Ralph

YES

34

William Street

Entire Road

YES

35

Windward Lane

off Riverbank - entire road

NO

36

Woodrow Street

Entire Road

YES

Free viewers are required for some of the attached documents.